Romerike Tunnel

Romerike Tunnel
Flytoget Airport Express Train at Etterstad
Overview
LineGardermoen Line
LocationØstmarka, Norway
SystemNorwegian railways
StartEtterstad
EndLillestrøm
Operation
Opened22 August 1999
OwnerBane NOR
OperatorFlytoget
SJ
SJ Norge
Vy
Vy Tåg
Technical
Line length14.580 km (9.060 mi)
No. of tracksDouble
Track gauge1,435 mm (4 ft 8+12 in)
Electrified15 kV  16.7 Hz AC
Operating speed210 km/h (130 mph)

The Romerike Tunnel (Norwegian: Romeriksporten) is a 14.580-kilometre (9.060 mi) railway tunnel in Norway between Oslo and Lillestrøm. It is the second longest railway tunnel in Norway after the Blix Tunnel opened in 2022, and forms the first section of the Gardermoen Line. It is double track and electrified, permitting speeds of 210 kilometres per hour (130 mph).

Construction started in 1994, with plans to open with the rest of the Gardermoen Line and Oslo Airport, Gardermoen on 8 October 1998. Due to serious leakage from Lutvann and several other lakes, it did not open until 22 August 1999. The leaks increased the cost of the tunnel from 0.5 billion kr to NOK 1.8 billion. The main contractor was Scandinavian Rock Group. The tunnel was originally owned by NSB Gardermobanen, then the Norwegian National Rail Administration, and now owned by Bane NOR. The tunnel allows long-distance, regional and Flytoget Airport Express Trains to bypass the old Hoved Line, reducing journey times between Oslo and Lillestrøm from 29 to 12 minutes.


From Wikipedia, the free encyclopedia · View on Wikipedia

Developed by Tubidy